How Long Do House Extensions Take in Bedfordshire?
If you’re planning house extensions, the first question is usually “how long will it take?” The honest answer depends on the size of the build, the design and the planning route. This guide goes through each stage, so you know what to expect before you start.
A house extension we built in Westoning, with large glass doors opening onto the patio.
How long do house extensions take from start to finish?
As a general guide, the building work takes these times, from starting on site to handover:
- Single-storey extension: 10 to 16 weeks
- Double storey extension: 16 to 24 weeks or more
- Side return extension: 8 to 14 weeks
- Larger wraparound extension: 14 to 22 weeks or more
Before building starts, you also need time for design, planning checks and building regulations. The exact time depends on the complexity and specification of the job.
What happens, and in what order?
- Design and drawings. You agree the layout, size and look. This usually takes a few weeks, depending on how quickly decisions are made.
- Planning route. Some extensions can go ahead under permitted development, but size limits and local rules apply, so check first. A householder planning application is usually decided within 8 weeks.
- Building regulations. Almost every extension needs approval. The council or an approved inspector checks the work at key stages, such as the foundations and the structure.
- Party wall notices. If you’re building on or near a neighbour’s boundary, notices must be served before work starts. The notice periods are usually one to two months, depending on the work.
- Groundworks and foundations. The site is marked out, dug and the foundations poured.
- The structure. Brickwork, steel beams, the roof, and the windows and doors.
- First fix and plastering. Electrics and plumbing go in, then the walls are plastered.
- Finishing. Flooring, decorating, final inspections and sign-off.
How soon can work start?
After an initial enquiry, we aim to arrange a site visit quickly. Once we have drawings or a specification and have visited the property, we generally aim to provide a detailed quotation within 7 to 14 days. Start dates depend on our programme and the size of the project, and we agree a commencement date with you before anything is finalised.
What slows house extensions down?
- Planning decisions. A waiting period can add weeks before work starts.
- Made-to-measure windows and doors. These are often ordered weeks ahead, so late orders hold up the build.
- Changing the design part-way through. Moving a wall or window after work starts costs time and money.
- Hidden problems. Old drains or poor ground are sometimes found once digging begins.
- Weather. Heavy rain can delay groundworks and roofing.
- Late finish choices. Waiting on tiles, flooring or kitchen decisions can stall the final stages.
Project spotlight: a house extension in Westoning
This house extension in Westoning has large dark-framed glass doors that open the room onto the patio. The cream rendered walls and red brickwork give it a clean, modern look, and the ceiling downlights light the new space.
Glazing like this is made to measure, so it has to be ordered early in the programme. That’s why door and window choices should be confirmed before the structure goes up.
How to keep your house extension on schedule
- Get a detailed written quotation and an agreed start date before anything begins.
- Check planning, building regulations and party wall needs early.
- Confirm windows, doors and finishes before the build begins.
- Avoid changing the design once work has started.
- Allow a couple of weeks of spare time for weather and surprises.
Common questions about house extensions
- Can I stay in the house during the build?
Usually, yes. Most extension work happens outside the existing house, although you may lose power or water for short periods, and the kitchen can be affected when the new space joins the old. - Do I need planning permission?
Not always, but it depends on the size, the position and the area you live in. Our planning and regulations guide explains the basics. - How much do house extensions cost?
It varies with size and finish. Read our guide to how much a house extension costs in Bedfordshire.
Planning house extensions in Bedfordshire, Buckinghamshire or Hertfordshire?
We plan and build house extensions for homeowners across the region. For a free site visit and a detailed written quote, call Sean on 07737 864684 or message us on WhatsApp. You can also read about our house extensions service, or see more about our work in Westoning.